Burrinjuck Dam – Transmission Tower Foundation Strengthening

Home / Case Study / Burrinjuck Dam – Transmission Tower Foundation Strengthening

Project Summary:

TransGrid required urgent remediation of aging transmission tower foundations before installing a new optical ground wire (OPGW) cable. PCA was contracted to provide a full design and construct solution for towers T125 and T126, which were suffering from severe anchor corrosion and posed a risk to safety and asset longevity.


Challenges

  • Remote mountainous terrain with limited access
  • No original design records or reliable geotechnical data
  • Corroded rock anchors requiring complete replacement
  • Concrete use infeasible due to transport restrictions
  • Fixed 7-week delivery window based on planned line outage
  • Unprecedented 10mm installation tolerance for micropiles (vs. 70mm industry standard)

Innovative Solution

PCA designed and installed a bespoke micropile system, each leg precisely connected with custom-fabricated steel brackets using finite element modelling (FEM). Key innovations included:

  • Custom steel templates to control micropile alignment
  • Helicopter-lifted equipment for Tower 125 access
  • Winch-slide access system for Tower 126
  • Modular lightweight machinery for remote transport
  • Prototype testing and FEM validation
  • World-first connection system, now patented globally

Outcome

  • Tower foundation life extended without environmental disruption
  • Precision alignment achieved with less than 10mm deviation
  • Delivered on time within a tight 7-week construction window
  • Eliminated the need for concrete batching in remote terrain
  • Set a new industry benchmark in transmission tower remediation

Project Type:

Civil

Client:

TransGrid

Main Contractors:

TransGrid

Project Engineers:

PCA Ground Engineering (Design & Construct Micropile Foundations)

Please fill in the form below and your requested case study will be forwarded to you.